Calculation dynamic key figures


<< Click to show table of contents >>

Navigation:  Key figures of value stream modeling > Simulation results (dynamic key figures) >

Calculation dynamic key figures


In this chapter all formulas used in the application for dynamic key figures are listed and described

 

Contents

1. Active time (Process)

2. Bottleneck KPI

3. Dynamic flow grade (for specific measurement section)

4. OEE (operating time, process)

5. OEE (simulation time, process)

6. OEE (simulation time, system)

7. Operating time (Process)

8. Theoretical number of workers

 

 

1. Active time (Process)

Formular

Description

\[ ActiveTime = Working+Setup+Failed+Reworking \]

times corresponding to process status portions

 

 

2. Bottleneck KPI

Formular

Description

\[ BottleneckKPI_{Process}= \frac{ActiveTime_{Process}}{OT_{Process}} \]

ActiveTimeProcess: (see above)

OTProcess: Operating time process (see below)

 

 

3. Dynamic flow grade (for specific measurement section)

Formular

Description

\[ FG_{dynamic, section}=\frac{avg, simulated\:TGT_{Parts}}{\sum staticProcessTimesInSection} \]

TGTParts: average of simulated throughout times for parts within measurement section (from start to finish object)

ProcessTimes: static calculated throughput times for value-adding processes within measurement section (Calculation corresponding to static object KPIs)

 

 

4. OEE (operating time, process)

Formular

Description

\[ OEE_{OT, Process}=\frac{\#IO\times CT_{Plan}}{OT}\times 100\% \]

#IO: Number of simulated IO parts as throughput of process

CTPlan: planned cycle time per process object (average if more than one product defined)

OT: Operating time process object (see below)

 

 

5. OEE (simulation time, process)

Formular

Description

\[ OEE_{SimTime, Process}=\frac{\#IO\times CT_{Plan}}{T_{Total}}\times 100\% \]

#IO: Number of simulated IO parts as throughput of process

CTPlan: planned cycle time per process (average if more than 1 product defined)

TTotal: Total simulation time

 

 

6. OEE (simulation time, system)

Formular

Description

\[ OEE_{SimTime, System}=\frac{\#IO\times TT_{avg}}{T_{Total}}\times 100\% \]

#IO: Number of simulated IO parts as throughput of system (added overall customer objects)

TTavg: average customer cycle time overall customer objects

TTotal: Whole simulation time

 

 

7. Operating time (Process)

Formular

Description

\[ OT=Working+Setup+Failed+Reworking+Waiting+Blocked \]

times corresponding to process status portions

 

 

8. Theoretical number of workers

Formular

Description

\[ \#W_{theo}= \#W\times \frac{ProcessUtilization}{100\%} \]

#W: number of workers per process object

ProcessUtilization, as:

\( ProcessUtilization=\frac{(Working+Setup+Failed)}{OT}\times 100\% \)

 

 