Production Schedule


<< Click to show table of contents >>

Navigation:  Parameterizing value stream objects > Object and product related settings >

Production Schedule


To create a new production schedule, one or more products must be added using the + button.

Existing products can be selected via the dropdown in the column Product, the columns Quantity and Duration have to be parameterized manually.

20230208_prod_schedule_1_EN

Figure 1 - Create production schedule

 

 

Existing entries can be moved by drag & drop or deleted by clicking on Delete (see figure 2)

20230208_prod_schedule_2_EN

Figure 2 - Moving entries

 

 

By clicking the Apply button, the production schedule is saved and displayed in the element (see Figure 3).

produktionsplan_element_festgelegt_1_EN

Figure 3.1 - Element without defined Production Schedule

produktionsplan_element_festgelegt_EN

Figure 3.1 - Element with defined Production Schedule

 

 


© SimPlan AG - Hanau District Court, Commercial Register (Part B) 6845 - info@simplan.de - www.simplan.de/en